目录
第一章 工程概况······················································································· 2
第二章 施工平面布置图············································································· 2
第三章 脚手架布置原则············································································· 2
第四章 脚手架所用材料············································································· 2
第五章 落地式脚手架施工········································································· 3
第六章 外脚手架搭设方法及其安全技术措施·············································· 4
第七章 脚手架验收···················································································· 5
第八章 落地式扣件钢管脚手架计算···························································· 5
第九章 外脚手架的拆除的安全技术措施··················································· 14
第十章 安全生产措施·············································································· 15
第十一章 文明施工措施··········································································· 17
(1)工程类型:该建筑工程为商业楼、公寓
地理位置及环境:本工程位于深圳市罗湖区梨园路,施工场地狭窄,施工车辆进出不便。
2、编制依据
(1)《建筑施工扣件式钢管脚手架安全技术规范》JGJ130-2011
(2)《建筑施工安全检查标准》……………………………JGJ59-2011
(3)《建筑施工高处作业安全技术》……………………JGJ80-1991
(4)《建筑施工手册》 (第四版)
(5)《建筑结构荷载规范》.................................................GB50009-2001
(6)甲方提供的建筑设计方案图
平面布置原则:平面布置力求科学、合理,充分利用有限的场地资源,最大限度的满足施工需要,确保既定的工期、安全生产、文明施工三大目标的实现。
材料堆放:为了保证现场材料堆放有序,材料尽可能按计划分期、分批、分层供应,尽量减少二次搬运。主要材料的堆放,应严格按照《施工现场平面布置图》确定的位置堆放整齐。
该脚手架搭设于AB座楼顶层,根据楼顶实际情况,搭设双排脚手架,根据本建筑物楼顶高度计算而定脚手架高度不小于7~8米。脚手架是后期搭设环形轨道施工的操作架和安全防护。
钢管:脚手架钢管采用外径48mm,壁厚3.2mm的焊接钢管,钢管的检查必须符合下列规定:具有产品质量合格证;钢管表面平直光滑,没有裂缝、结疤、分层、错位、硬弯、毛刺、压痕和深的划道;钢管外径、壁厚、端面等的偏差,符合《建筑施工扣件式钢管脚手架安全技术规范》的规定:外径±0.5mm、壁厚±10mm。
扣件:十字扣、回转扣符合规范要求,与钢管管径相匹配。扣件使用前进行质量检查,有裂缝、变形的严禁使用,出现滑丝的螺栓必须更换。
脚手板:脚手板使用竹笆脚手板(规格:1.2 ×0.85m )
安全网:必须是经国家指定监督检验部门监定许可生产的厂家产品。
立网:为密目网。(阻燃式安全网规格:1.8×6m )
材料机具计划表:
第五章 落地式脚手架施工
(1)钢管脚手架步距为1.8m,立杆间距为1.65m,脚手架宽1.3m,,连墙杆间距竖直3.5m,水平4~6m;里排立杆距建筑物0.8m。钢管立杆底座应垫木方(100×50×300沿柱距方向排列)并设置纵横方向扫地杆,连接于立杆上,离底部20cm左右。此脚手架高度未超过30m,立杆垂直偏差,不大于架高的1/200。
(2)立杆与大横杆要用十字扣件扣紧,不能隔离设置或遗漏;小横杆应靠近立杆布置,用十字扣件与大横杆扣紧;剪刀撑在脚手架外侧连续设置;剪刀撑斜杆与地面的倾角为45度一60度, 剪刀撑应联每次3—4根立杆,与在相邻两道剪刀撑之间,沿竖向每隔9—15m高加设一组长剪刀撑,并要将各道剪刀撑联结成整体,剪刀撑的两端除用旋转扣件与脚手架的立杆或大横杆扣紧外,中间增设2—4个扣接点,与之相交的立杆或大横杆扣紧。大横杆立面间距控制在2×0.9m左右,即步距为1.8m以便立网挂设,为了施工的安全在每层楼面标高处增设一步架,大横杆水平间距0.20m。
(3)连墙杆要设置在框架柱及梁等具有较好抗水平力作用的结构部位,经验算先将连墙杆的一端与300×250×15 mm预埋钢板焊牢,再用直径14的膨胀螺栓将钢板固定在框架柱及梁的结构部位,其垂直距离不大于3m也不得大于2个大横杆的步距;水平距离为4~6m,也不得大于立杆的4个步距;另一端与立杆连接。
(4)剪刀撑:每组剪刀撑立杆跨截止立杆根数为5根,5根立杆应设一组剪刀撑,剪刀撑与地面角度应不大于45—60之间,要连续搭接并保证搭接长度,相交点应处于同一和直线上。
(5)脚手板铺设要求:采用竹笆脚手板,平铺,不得高低不平(规格:1.2 ×0.85m )用12号铁丝将其绑在水平杆上,根据施工及安全要求沿步距高度层层铺设。
(6)挂安全网的要求:全封闭式安全立网(阻燃式安全网规格:1.8×5.8m ),封闭防护。
(7)水平安全硬防护要求:根据现场实际情况要求,安全硬防护高度不小于5m搭设;立杆按满堂脚手架基本要求搭设,每隔1.5m立杆与大横杆要用十字扣件扣紧,不能隔离设置或遗漏;钢管立杆底座应垫木方(100×50×300mm每根立柱设置一个),并设置纵横方向扫地杆,连接于立杆上,离底部200mm左右;每步横杆高度不得小于900mm布置;顶部采用双层钢管水平间距不小于400mm分别连接于横杆,下层钢管满铺减冲击力竹夹板,上层在满铺减冲击力竹夹板基础上再增设15mm厚的抗压力模板,上下两层间距为600mm;硬防护边缘按规范设置1.2m高安全防护围栏。
第六章 外脚手架搭设方法及其安全技术措施
1、地基处理应牢固可靠,垫木应通过设计计算并铺平稳不能有悬空,脚手杆底座应用钉子牢在垫木上,双立杆脚手架应使用双杆底座。
2、搭设顺序:安放垫木→摆放扫地杆→逐根树立立杆并与扫地杆扣紧→装扫地小横杆并与立杆和扫地杆扣紧→装第一步大横杆并与各立杆扣紧→安第一步小横杆→安第二步大横杆→安第二步小横杆→加设临时斜撑杆,上端与第二步大横杆扣紧(在装设连墙杆拆除)→安第三、四步大横杆和小横杆→安连墙杆→接立杆→加设剪刀撑→铺设脚手板→绑扎防护栏杆及挡脚板,并挂立网防护。
3、搭设要及时与结构拉结,或采用临时支顶以便确保搭设过程中的安全,并随搭随校正杆件的垂直度和水平偏差,同时适度拧紧扣件,螺栓的根部要放正,当用力矩搬手检查,应在40—50N.M之间,最大不能超过80N.M,连接大横杆的对接扣件,开口应朝架子内侧,螺栓要向上,以防雨水进入。
双排架的小横杆靠墙一端要离开墙面50—100mm,各杆件相交
出的端头,均要大于100mm,以防杆件滑脱。
剪刀撑的搭设要将一根斜杆扣在立杆上,另一根扣在小横杆的伸出部份上;斜杆两端扣件与立杆节点的距离不大于200mm。最下面的斜杆与立杆的连接点离地面不大于500mm。
外脚手架立杆基础外侧应挖排水沟,以防雨水浸泡地基。
钢管架应设置避雷针,分置于主楼外架四角立杆之上。并联通大横杆,形成避雷网络,并检测接地电阻不大于3Ω。外脚手架不得搭设在距离外电架空线路的安全距离内,并做好可靠的安全接地处理。
9、外脚手架必须及时维护加固,以达到坚固稳定,确保施工安全。
10、外脚手架严禁钢竹、钢木混搭,禁止扣件、绳索、铁丝混用。
11、外脚手架搭设人员必须持证上岗,并正确使用安全帽、安全带,穿防滑鞋。
12、严格控制施工荷载,脚手板不得集中堆料施工荷载,施工荷载不得大于2KN/m2。
13、控制扣件螺栓拧紧力矩,采用扭力板手,扭力矩应控制在40—50N.M范围内。
14、严禁脚手板存在探头挑,铺设脚手板以及多层作业时,应尽量使施工荷载内,外传递平衡。
15、保证脚手架体的整体的刚度和扰度,不得与井架,升降机一并拉结,不得截断架体。
16、雨天、五级以上大风停止高空作业,脚手架、马道、斜坡要采取防滑措施。大风过后,要对脚手架进行检查,预防高空坠落事故的发生。
17、采用与主体拉接,外用剪刀撑进行支撑拉结以防倾覆。
第七章 脚手架验收
1、外脚手架必须由持有效上岗证的人员搭设,随楼层的增高逐层对其进行检查及分段验收,不符合要求的迅速整改。
2、外脚手架分段验收应按JGJ59—99中“外脚手架检查评分表”所列项目和施工方案要求的内容进行检查,填写验收记录单,并由搭设人员、安全员、施工员、项目经理签证,方能交付使用。
第八章 落地式扣件钢管脚手架计算
落地架计算书
钢管脚手架的计算参照《建筑施工扣件式钢管脚手架安全技术规范》(JGJ130-2011)、
建筑地基基础设计规范》(GB 50007-2002)、《建筑结构荷载规范》(GB 50009-2011)、
《钢结构设计规范》(GB 50017-2003)等规范。
参数信息:
⑴.脚手架参数
搭设尺寸为:立杆的纵距为 1.65米,立杆的横距为1.35米,立杆的步距为1.80 米;
计算的脚手架为双排脚手架搭设高度为 8 米,立杆采用单立管;
内排架距离墙长度为0.30米;
大横杆在上,搭接在小横杆上的大横杆根数为 2;
采用的钢管类型为 Φ48×3.2;
横杆与立杆连接方式为单扣件;扣件抗滑承载力系数为 0.80;
连墙件采用两步三跨,竖向间距 3.60 米,水平间距4.95 米,采用膨胀螺栓连接;
⑵活荷载参数
施工荷载均布参数(kN/m2):3.000;脚手架用途:结构脚手架;
同时施工层数:2;
⑶风荷载参数
深圳地区,基本风压为0.45,风荷载高度变化系数μz为0.84,风荷载体型系数μs为0.65;
⑷.静荷载参数
每米立杆数承受的结构自重标准(kN/m2):0.1161;
脚手板自重标准值(kN/m2 ):0.350;栏杆挡脚板自重标准值(kN/m2):0.110;
安全设施与安全网(kN/m2 ):0.005;脚手板铺设层数:4;
脚手板类别:竹串片脚手板;栏杆挡板类别:栏杆冲压钢;
⑸地基参数
地基土类型:混凝土;地基承载力标准值(kN/m2):500.00;
基础底面扩展面积(m2):0.09;基础降低系数:0.40。
1、大横杆的计算:
大横杆按照三跨连续梁进行强度和挠度计算,大横杆在小横杆的上面。
按照大横杆上面的脚手板和活荷载作为均布荷载计算大横杆的最大弯矩和变形。
⑴.均布荷载值计算
大横杆的自重标准值:P1=0.035 kN/m ;
脚手板的荷载标准值:P2=0.350×1.000/(2+1)=0.117 kN/m ;
活荷载标准值: Q=3.000×1.000/(2+1)=1.000 kN/m;
静荷载的计算值: q1=1.2×0.035+1.2×0.117=0.182 kN/m;
活荷载的计算值: q2=1.4×1.000=1.400 kN/m;
大横杆计算荷载组合简图(跨中最大弯矩和跨中最大挠度)
大横杆计算荷载组合简图(支座最大弯矩)
⑵强度计算
最大弯矩考虑为三跨连续梁均布荷载作用下的弯矩
跨中最大弯距计算公式如下:
跨中最大弯距为M1max=0.08×0.182×1.6502+0.10×1.400×1.6502 =0.421 kN.m;
支座最大弯距计算公式如下:
支座最大弯距为 M2max= -0.10×0.182×1.6502-0.117×1.400×1.6502 =-0.496 kN.m;
我们选择支座弯矩和跨中弯矩的最大值进行强度验算:
σ=Max(0.421×106,0.496×106)/4730.0=104.863 N/mm2;
大横杆的抗弯强度:σ= 104.863 N/mm2 小于 [f]=205.0 N/mm2。满足要求!
⑶挠度计算:
最大挠度考虑为三跨连续梁均布荷载作用下的挠度
计算公式如下:
静荷载标准值: q1= P1+P2=0.035+0.117=0.152 kN/m;
活荷载标准值: q2= Q =1.000 kN/m;
三跨连续梁均布荷载作用下的最大挠度
V= 0.677×0.152×1650.04/(100×2.06×105×113600.0)+0.990×1.000
×1650.04/(100×2.06×105×113600.0) = 3.462 mm;
脚手板,纵向、受弯构件的容许挠度为 l/150与10 mm 请参考规范表5.1.8。
大横杆的最大挠度小于 1650.0/150 mm 或者 10 mm,满足要求!
2、小横杆的计算:
小横杆按照简支梁进行强度和挠度计算,大横杆在小横杆的上面。
用大横杆支座的最大反力计算值,在最不利荷载布置下计算小横杆的最大弯矩和变形。
⑴荷载值计算
大横杆的自重标准值:p1= 0.035×1.650 = 0.058 kN;
脚手板的荷载标准值:P2=0.350×1.000×1.650/(2+1)=0.192 kN;
活荷载标准值:Q=3.000×1.000×1.650/(2+1) =1.650 kN;
荷载的计算值: P=1.2×(0.058+0.192)+1.4 ×1.650 = 2.611 kN;
小横杆计算简图
⑵强度计算
最大弯矩考虑为小横杆自重均布荷载与荷载的计算值最不利分配的弯矩和
均布荷载最大弯矩计算公式如下:
Mqmax = 1.2×0.035×1.0002/8 = 0.005 kN.m;
集中荷载最大弯矩计算公式如下:
Mpmax = 2.611×1.000/3 = 0.870 kN.m ;
最大弯矩 M= Mqmax + Mpmax = 0.876 kN.m;
σ = M / W = 0.876×106/4730.000=185.132 N/mm2 ;
小横杆的计算强度小于 205.000 N/mm2,满足要求!
⑶挠度计算
最大挠度考虑为小横杆自重均布荷载与荷载的计算值最不利分配的挠度和
小横杆自重均布荷载引起的最大挠度计算公式如下:
Vqmax=5×0.035×1000.04/(384×2.060×105×113600.000) = 0.020 mm ;
P2 = p1 + p2 + Q = 0.058+0.192+1.650 = 1.901 kN;
集中荷载标准值最不利分配引起的最大挠度计算公式如下:
Vpmax = 1900.910×1000.0×(3×1000.02-4×1000.02/9 ) /(72×2.060×105
×113600.0) = 2.883 mm;
最大挠度和 V = Vqmax + Vpmax = 0.020+2.883 = 2.903 mm;
小横杆的最大挠度小于 (1000.000/150)=6.667 与 10 mm,满足要求!;
3、扣件抗滑力的计算:
按规范表5.1.7,直角、旋转单扣件承载力取值为8.00kN,按照扣件抗滑承载力系数0.80,
该工程实际的旋转单扣件承载力取值为6.40kN。
纵向或横向水平杆与立杆连接时,扣件的抗滑承载力按照下式计算(规范5.2.5):
R ≤ Rc
其中 Rc -- 扣件抗滑承载力设计值,取6.40 kN;
R -- 纵向或横向水平杆传给立杆的竖向作用力设计值;
横杆的自重标准值: P1 = 0.035×1.000=0.035 kN;
脚手板的荷载标准值: P2 = 0.350×1.000×1.650/2=0.289 kN;
活荷载标准值: Q = 3.000×1.000×1.650 /2 = 2.475 kN;
荷载的计算值: R=1.2×(0.035+0.289)+1.4×2.475=3.854 kN;
R < 6.40 kN , 单扣件抗滑承载力的设计计算满足要求!
脚手架荷载标准值:
作用于脚手架的荷载包括静荷载、活荷载和风荷载。静荷载标准值包括以下内容:
(1)每米立杆承受的结构自重标准值(kN/m);本例为0.1292
NG1 = 0.129×29.000 = 3.747 kN;
(2)脚手板的自重标准值(kN/m2);本例采用竹串片脚手板,标准值为0.35
NG2= 0.350×4×1.650×(1.000+0.3)/2 = 1.501 kN;
(3)栏杆与挡脚手板自重标准值(kN/m);本例采用栏杆冲压钢,标准值为0.11
NG3 = 0.110×4×1.650/2 = 0.363 kN;
(4)吊挂的安全设施荷载,包括安全网(kN/m2);0.005
NG4 = 0.005×1.650×29.000 = 0.239 kN;
经计算得到,静荷载标准值
NG =NG1+NG2+NG3+NG4 = 5.851 kN;
活荷载为施工荷载标准值产生的轴向力总和,内、外立杆按一纵距内施工荷载总和的1/2
取值。
经计算得到,活荷载标准值
NQ= 3.000×1.000×1.650×2/2 = 4.950 kN;
风荷载标准值应按照以下公式计算
其中 Wo -- 基本风压(kN/m2),按照《建筑结构荷载规范》(GB50009-2001)的规定采用:
Wo = 0.450 kN/m2;
Uz -- 风荷载高度变化系数,按照《建筑结构荷载规范》(GB50009-2001)的规定采用:
Uz= 0.840 ;
Us -- 风荷载体型系数:Us =0.649 ;
经计算得到,风荷载标准值
Wk = 0.7 ×0.450×0.840×0.649 = 0.172 kN/m2;
不考虑风荷载时,立杆的轴向压力设计值计算公式
N = 1.2NG+1.4NQ= 1.2×5.851+ 1.4×4.950= 13.951 kN;
考虑风荷载时,立杆的轴向压力设计值计算公式
N = 1.2 NG+0.85×1.4NQ = 1.2×5.851+ 0.85×1.4×4.950= 12.911 kN;
风荷载设计值产生的立杆段弯矩 MW计算公式
Mw = 0.85 ×1.4WkLah2/10 =0.850 ×1.4×0.172×1.650×
1.8002/10 = 0.109 kN.m;
4、立杆的稳定性计算:
不组合风荷载时,立杆的稳定性计算公式为:
立杆的轴心压力设计值 :N =13.951 kN;
计算立杆的截面回转半径 :i = 1.59 cm;
计算长度附加系数 :K = 1.155 ;
计算长度系数参照《扣件式规范》表5.3.3得 :U = 1.500
计算长度 ,由公式 lo = kuh 确定 :lo = 3.119 m;
Lo/i = 196.000 ;
轴心受压立杆的稳定系数φ,由长细比 lo/i 的结果查表得到 :φ= 0.188 ;
立杆净截面面积 : A = 4.50 cm2;
立杆净截面模量(抵抗矩) :W = 4.73 cm3;
钢管立杆抗压强度设计值 :[f] =205.000 N/mm2;
σ = 13951.000/(0.188×450.000)=164.901 N/mm2;
立杆稳定性计算 σ = 164.901 小于 [f] = 205.000 N/mm2 满足要求!
考虑风荷载时,立杆的稳定性计算公式
立杆的轴心压力设计值 :N =12.911 kN;
计算立杆的截面回转半径 :i = 1.59 cm;
计算长度附加系数 : K = 1.155 ;
计算长度系数参照《扣件式规范》表5.3.3得 :U = 1.500
计算长度 ,由公式 lo = kuh 确定:lo = 3.119 m;
Lo/i = 196.000 ;
轴心受压立杆的稳定系数φ,由长细比 lo/i 的结果查表得到 :φ= 0.188
立杆净截面面积 : A = 4.50 cm2;
立杆净截面模量(抵抗矩) :W = 4.73 cm3;
钢管立杆抗压强度设计值 :[f] =205.000 N/mm2;
σ = 12911.160/(0.188×450.000)+109247.235/4730.000 = 175.711 N/mm2;
立杆稳定性计算 σ = 175.711 小于 [f] = 205.000 N/mm2 满足要求!
5、最大搭设高度的计算:
不考虑风荷载时,采用单立管的敞开式、全封闭和半封闭的脚手架可搭设高度按照下式计算:
构配件自重标准值产生的轴向力 NG2K(kN)计算公式为:
NG2K = NG2+NG3+NG4 = 2.104 kN;
活荷载标准值 :NQ = 4.950 kN;
每米立杆承受的结构自重标准值 :Gk = 0.129 kN/m;
Hs =[0.188×4.500×10-4×205.000×103-(1.2×2.104
+1.4×4.950)]/(1.2×0.129)=50.880 m;
脚手架搭设高度 Hs等于或大于26米,按照下式调整且不超过50米:
[H] = 50.880 /(1+0.001×50.880)=48.417 m;
[H]= 48.417 和 50 比较取较小值。得到,脚手架搭设高度限值 [H] =48.417 m。
考虑风荷载时,采用单立管的敞开式、全封闭和半封闭的脚手架可搭设高度按照下式计算:
构配件自重标准值产生的轴向力 NG2K(kN)计算公式为:
NG2K = NG2+NG3+NG4 = 2.104 kN;
活荷载标准值 :NQ = 4.950 kN;
每米立杆承受的结构自重标准值 :Gk = 0.129 kN/m;
计算立杆段由风荷载标准值产生的弯矩: Mwk=Mw / (1.4×0.85) = 0.109 /(1.4 × 0.85) = 0.092 kN.m;
Hs =( 0.188×4.500×10-4×205.000×10-3-(1.2×2.104+0.85×1.4×(4.950+
0.188×4.500×0.092/4.730)))/(1.2×0.129)=44.982 m;
脚手架搭设高度 Hs等于或大于26米,按照下式调整且不超过50米:
[H] = 44.982 /(1+0.001×44.982)=43.046 m;
[H]= 43.046 和 50 比较取较小值。经计算得到,脚手架搭设高度限值 [H] =43.046 m。
6、连墙件的计算:
连墙件的轴向力计算值应按照下式计算:
Nl = Nlw + No
风荷载基本风压值 Wk = 0.172 kN/m2;
每个连墙件的覆盖面积内脚手架外侧的迎风面积 Aw = 17.820 m2;
连墙件约束脚手架平面外变形所产生的轴向力(kN), No= 5.000 kN;
风荷载产生的连墙件轴向力设计值(kN),应按照下式计算:
NLw = 1.4×Wk×Aw = 4.284 kN;
连墙件的轴向力计算值 NL= NLw + No= 9.284 kN;
其中 φ -- 轴心受压立杆的稳定系数,l为内排架距离墙的长度,
由长细比 l/i=600.000/15.900的结果查表得到0.893;
A = 4.50 cm2;[f]=205.00 N/mm2;
连墙件轴向力设计值 Nf=φ×A×[f]=0.893×4.500×10-4×205.000×103 = 82.379 kN;
Nl=9.284<Nf=82.379,连墙件的设计计算满足要求!
连墙件采用膨胀螺栓连接,预埋铁的计算参见《施工计算手册》钢结构部分。
立杆的地基承载力计算:
立杆基础底面的平均压力应满足下式的要求
p ≤ fg
地基承载力设计值:
fg = fgk×Kc = 200.000 kN/m2;
其中,地基承载力标准值:fgk= 500.000 kN/m2 ;
脚手架地基承载力调整系数:kc = 0.400 ;
立杆基础底面的平均压力 ,p = N/A =143.457 kN/m2 ;
其中,上部结构传至基础顶面的轴向力设计值 :N = 12.911 kN;
基础底面面积 (m2):A = 0.090 m2 。
p=143.457 ≤ fg=200.000 kN/m2 。地基承载力的计算满足要求!
第九章 外脚手架的拆除的安全技术措施
1、架子拆除时应划分作业区,周围设围栏或竖立警戒标志,并设专人警戒,地面设有专人指挥,严禁非作业人员入内。
2、拆除的高处作业人员,必须戴安全帽,系安全带,扎裹腿,穿软底鞋。
3、拆除顺序应遵循由上而下,先搭后拆,后搭先拆的原则。即先拆栏杆、脚手板、剪刀撑、斜撑,后拆小横杆、大横杆、立杆等,并按一步一清的原则依次进行,要严禁上下同时进行拆除作业。
4、拆立杆时,应先抱住立杆再拆开最后两个扣,拆除大横杆,斜撑、剪刀撑时,先拆中间扣,然后托住中间,再解端头扣。
5、连墙点应随拆除进度逐层拆除,拆抛撑前,应设置临时支撑,然后再拆抛撑。
6、拆除时要统一指挥,上下呼应,动作协调,当解开与另一人有关的结扣时,应先通知对方,以防坠落。
7、在大片架子拆除前应将预留的斜道、上料平台、通道小飞跳等,先行加固,以便拆除后能确保其完整、完全和稳定。
8、拆除地如附近有外电线路,要采取隔离措施,严禁架杆接触电线。
9、拆除时不应碰坏门窗、玻璃、水落管、地下明沟等物品。
10、拆下的材料,应用绳栓住,利用滑轮徐徐下运,严禁抛掷,运至地面的材料应按指定地点,随拆随运,分类堆放,当天拆当天清,拆下的扣件或铁丝要集中回收处理。
11、在拆架过程中,不得中途换人,如必须换人时,应将拆除情况交代清楚后方可离开。
第十章 安全生产措施
我们将严格按照标准要求保证本工程安全生产零事故,搞好安全生产。
建立健全安全生产岗位责任制,组建完善的安全管理保证体系,工程开工前组织工作人员学习管理体系支持性文件中的《安全生产管理条例》对参加上岗的职工进行上岗安全教育,增加自我保护能力,使每个职工自觉遵守安全规程,严格遵守各项安全管理制度,项目经理全面负责该工程的安全管理工作,按照建筑面积的比例配备专职安全管理人员和兼职安全管理人员,专职安全员具体负责安全工作,工长在安全生产过程中要首先抓好安全生产,在施工前工地项目经理要对现场施工人员进行一次全面的安全技术交底,并在工作中对安全工作达到人人管安全,人人重视安全,集体实现安全生产工作。并设立安全宣传牌,张贴标语口号创造现场安全气氛。
坚持作好“三宝”“四口”安全保护措施,进入工地时必须戴好安全帽,在高空作业中必须系好安全带,按规定设制好安全防护水平网,底层通道口,固定出入通道应搭设防护棚,棚宽大于道口。
安全网应按市建筑施工现场安全防护基本标准设制,首层按规定宽度(一般6m),平支双层安全网,首层各出入口应搭设护头棚,外墙施工采用全封闭式安全管理方法,采用密目式安全网封闭,脚步手架采用钢脚手架。
脚手架操作平台的搭设必须符合规定要求,所有扣件应拧紧。架子与建筑物应拉接绑牢,并随时检查其牢固性,在施工中不得超载和集中堆放,拆卸脚手架应有专人监护,并设警戒标志。
夜间应保证场地照明,设制警示红灯。施工中设备必须按操作规程进行作业,杜绝“三违”现象,操作人员必须经过培训,全部达到持证上岗,在作业中应精力集中,严格执行岗位责任制,及时发现和处理机电设备故障,保持设备完好率,杜绝超载和违章现象。
现场施工用电应按《施工现场临时用电安全技术规范》(JGJ46-88)执行,达到“三相、五线”制,按照三级配电,二级保护的原则配制临时用电,每台设备执行“一机、一闸、一漏、一箱”的原则,各类机电设备应设接地、接零以杜绝触电事故的发生,所有电源、电闸箱应有门、有锁、有防雨盖板、有危险标志。
现场照明:
一般场所采用220V电压,危险、潮湿场所和金属容器内的照明及手持照明灯具,应采用符合要求的安全电压。
照明导线应用绝缘子固定,严禁使用花线或塑料胶质线,导线不得随地拖拉或绑在脚手架上。
照明灯具的金属外壳必须接地或接零,单相回路内的照明开关箱必须装设漏电保护器。
室外照明灯具距地面不得低于3m,室内距地面不得低于2.4m。碘钨灯固定架设,要保证安全。钠、铊等金属卤化物灯具的安装高度宜在5m以上,灯线不得靠近灯具表面。
架空线:
架空线必须设在专用电杆(水泥杆、木杆)上,严禁架设在树或脚手架上。
架空线应装设横担和绝缘子,其规格、线间距离、档距等应符合架空线路要求,其电杆板线离地2.5m以上应加绝缘子。
架空线一般应离地4m以上,机动车道为6m以上。
电箱(配电箱、开关箱):
电箱应有门、锁、色标和统一编号。
电箱内开关电器必须完整无损,接线正确,各类接触装置灵敏可靠,绝缘良好,无积灰、杂物,箱体不得歪斜。
电箱安装高度和绝缘材料等均应符合规定。
电箱内应设置漏电保护器,选用合理的额定漏电动作电流进行分极配合。
配电箱应设总熔丝、分熔丝、分开关,零排地排齐全,动力和照明分别设置。
配电箱的开关在电器应与配电线或开关箱一一对应配合,作分路设置,以确保专路主控,总开关电器与分路开关电器的额定值、动作整定值相适应,熔丝应和用电设备的实际负荷相匹配。
金属外壳电箱应作接地或接零保护。
开关箱与用电设备实行一机一闸一保险。
同一移动开关箱严禁配有380V和220V两种电压等级。
接地接零:
接地体可用角钢、圆钢或钢管,但不得用螺纹钢,其截面不小于480mm2,一组2根接地体之间间距不小于2.5m,入土深不小于2m,接地电阴应符合规定。
橡、皮线中黑色或绿/黄双色线作为接地线,与电气设备相连接或接零线截面最小不能低于2.5 mm2,多股芯线,手持式民用电设备应采用不小于1.5 mm2的多股铜芯线。
电杆转角杆、终端杆及总箱、分配电箱必须有重复接地。
高层配电箱重设接地,必须从地下引入。
做好电气设备的防雨防止因雨水发生短路而损坏线路和设备,以免发生触电事故。
所有电机、电气线路、水网要设专人负责经常检查,发生问题及时解决消除隐患,另外按规程标准要求设备闸箱上锁,设专人经常检查漏电保护装置的灵敏情况和其它运行使用情况。
第十一章 文明施工措施
我公司对施工现场文明施工有严格的规定,有统一的对外宣传方式,有蕴含多年施工经历的企业文化,我们决心将企业多年来形成的优良的作风带到本工程施工现场。
班组落手清:班组必须做好操作落手清,随作随清,物尽其用,在施工作业时,应有防止尘土飞扬、泥浆洒漏、污水外流、车辆沾带泥土运行等措施,有考核制度,定期检查评分考核,成绩上牌公布。
生活卫生:
1、生活卫生应纳入工地总体规则,落实卫生专(兼)职管理人员和保洁人员,落实责任制。
2、施工现场须设有饮水桶,做到有盖加配杯子,有消毒设备(除沙滤水外)。
3、生活垃圾必须随时处理或集中加以遮挡,妥善处理,保持场容整洁。
针对本工程而制定的具体措施:
1、本工程的施工现场位于深圳市罗湖区,现场施工必须达到《示范文明施工现场的标准》,严格按照省市有关文明施工法规的条款为标准,以创建文明施工工地为目标,决不影响周边环境,严格遵守各项规章制度。
2、成立以项目经理挂帅的文明施工保证体系,制定有关规章制度和奖罚条例,广泛利用宣传板,标语等形式开展宣传教育,使文明施工成为参于施工活动的每一名同志的一种自觉行为,贯穿于工程施工的全过程。
3、施工操作现场做到工完场清,建筑物内外的生产、生活垃圾及残土当日清理运出场外,保证场内清洁。
4、施工期间,严格控制机械噪声,教育工人不许吵闹和大声喧哗,夜间施工要有夜间施工许可证,采取有效措施并设专人负责,有管理制度。
5、施工现场所用明火,设专人负责,有管理制度,杜绝对环境的污染。
6、服从甲方、监理及总包单位的管理,自觉遵守有关的各规定。